Fault Simulation
6.2 Mode 2 (3-phase) Charging Cable
Switch mains voltage on by turning the top rotary selector switch (S1) to the
Status C position (system state: vehicle ready for charging).
6.2.1 Simulated Interruption
Start with the bottom rotary selector switch (S2) in the first ON position in the green area
for single-phase interruption.
Switch through the positions, one after the other, in the clockwise direction (table from
top to bottom). Conductor interruption using a 3-phase, mode 3 charging cable as an
example:
Note
Tripping performance may deviate from this example in the case of ICCBs from other man-
ufacturers – adhere to the manufacturer’s test instructions!
6.2.2 Simulation of PE to Phase (PE-U
EXT
)
Set the bottom rotary selector switch (S2) to the PE-U
EXT
position.
Step 18: see section “Protective Conductor Current Measurement (IPE) at Mode 2
Charging Cable” on page 15
Step
Rotary
switch
Test Adapter
ICCB
Action
L1
LED
LED
L2
LED
L3
N
LED
PE
LED
LED
1
The test object’s correct reaction to the simulated fault can
be found in the manufacturer’s operating instructions.
2
3
4
5
6
7
8
Regarding step 8: The N LED also lights up due to star con-
nection, although N is interrupted!
9
10
Step
Rotary switch
Test Adapter
ICCB-IN1
Action
L1
LED
LED
L2
LED
L3
N
LED
PE
LED
LED
11
The test object’s correct reaction to the simu-
lated fault can be found in the manufacturer’s
operating instructions.

Bekijk gratis de handleiding van Gossen Metrawatt PROFITEST EMOBILITY, stel vragen en lees de antwoorden op veelvoorkomende problemen, of gebruik onze assistent om sneller informatie in de handleiding te vinden of uitleg te krijgen over specifieke functies.

Productinformatie

MerkGossen Metrawatt
ModelPROFITEST EMOBILITY
CategorieNiet gecategoriseerd
TaalNederlands
Grootte2912 MB