19 | Commissioning
Installer and user reference guide
71
FXNA-A
VRV system air conditioner
4P785124-1 – 2024.09
19 Commissioning
NOTICE
General commissioning checklist. Next to the commissioning instructions in this
chapter, a general commissioning checklist is also available on the Daikin Business
Portal (authentication required).
The general commissioning checklist is complementary to the instructions in this
chapter and can be used as a guideline and reporting template during commissioning
and hand-over to the user.
In this chapter
19.1 Overview: Commissioning ...................................................................................................................................................... 71
19.2 Precautions when commissioning.......................................................................................................................................... 71
19.3 Checklist before commissioning............................................................................................................................................. 72
19.4 To perform a test run ............................................................................................................................................................. 72
19.1 Overview: Commissioning
This chapter describes what you have to do and know to commission the system
after it is installed.
Typical workflow
Commissioning typically consists of the following stages:
1 Checking the "Checklist before commissioning".
2 Performing a test run for the system.
19.2 Precautions when commissioning
NOTICE
Before starting up the system, the unit MUST be energised for at least 6 hours to
avoid compressor breakdown during startup.
NOTICE
ALWAYS operate the unit with thermistors and/or pressure sensors/switches. If NOT,
burning of the compressor might be the result.
NOTICE
ALWAYS complete the refrigerant piping of the unit before operating. If NOT, the
compressor will break.
NOTICE
Cooling operation mode. Perform the test run in cooling operation mode so that
stop valves failing to open can be detected. Even if the user interface was set to
heating operation mode, the unit will run in cooling operation mode during 2‑3
minutes (although the user interface will display the heating icon), and then
automatically switch to heating operation mode.
Bekijk gratis de handleiding van Daikin FXNA32A2VEB, stel vragen en lees de antwoorden op veelvoorkomende problemen, of gebruik onze assistent om sneller informatie in de handleiding te vinden of uitleg te krijgen over specifieke functies.
Productinformatie
| Merk | Daikin |
| Model | FXNA32A2VEB |
| Categorie | Niet gecategoriseerd |
| Taal | Nederlands |
| Grootte | 10681 MB |