• The ground at the installation site must be compacted enough. Relative compaction of
the ground should be equal to or greater than 98%. Otherwise, take proper methods to
strengthen the ground.
5.3.2 Recommended Foundation Construction Plan
The following conditions must be fulfilled:
• The bottom of the foundation should be firm enough.
• The foundations must be suitable for the weight of the MV Station.
• The foundation should be higher than the pea gravel ground on site to prevent the rain
from damaging the base or penetrating into the MV Station.
• Sufficient cross-sectional area and depth of the foundation should be maintained. The
depth is designed according to local soil conditions.
• Cable route should be taken into account.
• The LV cable trench must have enough space for personnel to enter.
• Backfill after securing cable clamps and connecting cables.
Overall construction effect is shown below.
The foundation plan described in this chapter is for reference only, For the specific design,
refer to the drawing provided by the design institute.
No
Name Part source
A Foundation
Not in the scope of delivery
B Oil tray
C Pea gravel ground
D Platform
System Manual 5 Mechanical Installation
27
Bekijk gratis de handleiding van Sungrow MVS4500-LV, stel vragen en lees de antwoorden op veelvoorkomende problemen, of gebruik onze assistent om sneller informatie in de handleiding te vinden of uitleg te krijgen over specifieke functies.
Productinformatie
| Merk | Sungrow |
| Model | MVS4500-LV |
| Categorie | Niet gecategoriseerd |
| Taal | Nederlands |
| Grootte | 9056 MB |