BMT-P2/144A(550W)P30
STANDARD INSTALLATION MANUAL FOR POLARIS 580W (HOOP INSTALLATION)
copper wire to connect the grounding row of the equipment to the grounding electrode across.
Note:
This conductive layer on the inside of the glass cover cannot be repaired once it is damaged,
and can cause signicant power loss.
Grounding resistance measurement:
● The comprehensive grounding resistance value of the system is required to be no more than
4Ω
Pre-commissioning check
● Connect the product array, inveer and AC grid correctly according to the installation
procedure described previously. Ensure that the AC and DC side voltages meet the machine
sta-up conditions.
Product array
● Before the inveer is turned on and running, the product array on the site needs to be
checked to see if the open circuit voltage of each product meets the requirements.
① Record all measured values on site accurately.
② Ensure that the positive and negative polarity is correct, otherwise the machine can be
seriously damaged.
③ Use megohmmeter to test the positive pole and negative pole of each product array to the
eah insulation resistance> 40MΩ.
Newsletter and Accessories
● Check whether the communication cable is properly and rmly connected, and whether the
shield is well grounded (preferably with double-ended grounding).
Network
● Checking whether the network can be connected to the outside (sending data).
● Check if you can read data from external connections (remote seices).
Power generation trial run
● Ensure that the above inspection items meet the requirements.
● Close the DC input side circuit breaker.
● Close the grid-side circuit breaker.
● The inveer will sta itself and generate electricity on the grid when the conditions required
for normal operation of the machine are met.
● The grid-connected inveer requires no human control after normal operation and has
automatic shutdown and sta-up functions after a fault.
Shutdown process
● The grid-connected inveers will shut down when the sun is not enough to generate
electricity.
● Emergency shutdown process: When there is a danger of electric shock to personnel or
Bekijk gratis de handleiding van Goodwe Polaris BMT-P2/144A, stel vragen en lees de antwoorden op veelvoorkomende problemen, of gebruik onze assistent om sneller informatie in de handleiding te vinden of uitleg te krijgen over specifieke functies.
Productinformatie
| Merk | Goodwe |
| Model | Polaris BMT-P2/144A |
| Categorie | Niet gecategoriseerd |
| Taal | Nederlands |
| Grootte | 8693 MB |