07 Equipment Commissioning
User Manual V1.2-2024-10-30
7�2 Power On
Step 1 Turn on the battery breaker of the inverter.
Step 2 Turn on the MPPT input breaker of the inverter(Only for ETC series).
Step 3 Turn on the AC breaker of the inverter.
7 Equipment Commissioning
7�1 Check Before Power ON
No� Check Item
1
The inverter is rmly installed at a clean place that is well-ventilated and easy to
operate.
2
The PE cable, DC input cable, battery cable, AC output cable, and communication
cable are connected correctly and securely.
3 Cable ties are intact, routed properly and evenly.
4
The voltage and frequency at the connection point meet the inverter grid
connection requirements.
5 The door of the wiring compartment is locked.
6 All the upstream and downstream breakers are disconnected.
Bekijk gratis de handleiding van Goodwe GW50K06-ETC, stel vragen en lees de antwoorden op veelvoorkomende problemen, of gebruik onze assistent om sneller informatie in de handleiding te vinden of uitleg te krijgen over specifieke functies.
Productinformatie
| Merk | Goodwe |
| Model | GW50K06-ETC |
| Categorie | Niet gecategoriseerd |
| Taal | Nederlands |
| Grootte | 8531 MB |