07 Equipment Commissioning
User Manual V1.2-2024-10-30
7�2 Power On
Step 1 Turn on the battery breaker of the inverter.
Step 2 Turn on the MPPT input breaker of the inverter(Only for ETC series).
Step 3 Turn on the AC breaker of the inverter.
7 Equipment Commissioning
7�1 Check Before Power ON
No� Check Item
1
The inverter is rmly installed at a clean place that is well-ventilated and easy to
operate.
2
The PE cable, DC input cable, battery cable, AC output cable, and communication
cable are connected correctly and securely.
3 Cable ties are intact, routed properly and evenly.
4
The voltage and frequency at the connection point meet the inverter grid
connection requirements.
5 The door of the wiring compartment is locked.
6 All the upstream and downstream breakers are disconnected.

Bekijk gratis de handleiding van Goodwe GW50K06-ETC, stel vragen en lees de antwoorden op veelvoorkomende problemen, of gebruik onze assistent om sneller informatie in de handleiding te vinden of uitleg te krijgen over specifieke functies.

Productinformatie

MerkGoodwe
ModelGW50K06-ETC
CategorieNiet gecategoriseerd
TaalNederlands
Grootte8531 MB