30 | ELCO GmbH
Assembly
Operation manual 50.0 | Status 10.2021
5.3.11 Checking the connections
Once the assembly process is complete, the following
points must be checked:
B Leak-tightness of all lines.
B Flexibility of all lines to the generation unit.
B Tight fit of all connections in the control cabinet.
B No damage, kinks or pinches in the cabling and
lines.
B The siphon of the condensate drain is filled with
water.
B Tension-free installation of all lines to the generation
unit.
B Clockwise rotating field.
A Check the system.
If the exhaust air and flue gas are extracted together:
A Ensure that the system is fitted with a suitable
exhaust air kit.
If the exhaust air or flue gas is extracted in combination
with another heat source (peak load boiler or another
system):
A Ensure that the system is fitted with a suitable
backflow preventer.
Following assembly, the commissioning of the system
can be arranged with the manufacturer (or a specialist
partner authorised by the manufacturer).
Commissioning request.
Download forms:
Ј
www.elco.net
A Arrange a time and date for the commissioning.

Bekijk gratis de handleiding van Elco VARION C-POWER, stel vragen en lees de antwoorden op veelvoorkomende problemen, of gebruik onze assistent om sneller informatie in de handleiding te vinden of uitleg te krijgen over specifieke functies.

Productinformatie

MerkElco
ModelVARION C-POWER
CategorieNiet gecategoriseerd
TaalNederlands
Grootte5865 MB