This process shall be repeated until no refrigerant is within
the system. When the final OFN charge is used, the system
shall be vented down to atmospheric pressure to enable
work to take place.
This operation is absolutely vital if brazing operations on
the pipe-work are to take place.
• Ensure that the outlet for the vacuum pump is not close to
any ignition sources and there is ventilation available.
13.Charging procedures
• In addition to conventional charging procedures, the follow-
ing requirements shall be followed:
–Ensure that contamination of different refrigerants does
not occur when using charging equipment.
–Hoses or lines shall be as short as possible to minimise
the amount of refrigerant contained in them.
–Cylinders shall be kept upright.
–Ensure that the refrigeration system is earthed prior to
charging the system with refrigerant.
–Label the system when charging is complete (if not
already).
–Extreme care shall be taken not to overfill the
refrigeration system.
• Prior to recharging the system it shall be pressure tested
with OFN.
The system shall be leak tested on completion of charging
but prior to commissioning.
A follow up leak test shall be carried out prior to leaving the
site.
14.Decommissioning
• Before carrying out this procedure, it is essential that the
technician is completely familiar with the equipment and all
its detail.
• It is recommended good practice that all refrigerants are
recovered safely.