Step 7: Lower the load to the ground/supporting surface (photos 11 and 12). Position the object above
the surface that will receive it (ground, pallet, work platform, etc.). Make sure that the load is not swinging
or rotating before beginning to lower it.
11 12
Step 8
: Once the load has been fully lowered, immobilize it. Disengage the pipe grab by lifting one or both of
the pipe guide weldments. Raise the grab so that it is completely free of the load.
13
14
15
16
Maintenance and Inspections:
A designated person must verify that the device complies with all regulations, codes, and standards that
apply to “Under-the-Hook Lifting Devices” in the location where the pipe grab is used. The person
designated to conduct inspections must do so before
the pipe grab is used for the first time, and EACH
time the grab is installed for use.
Inspections:
The end-user is responsible for performing inspections as recommended in ASME B30.20,
which categorizes examinations based on regularity of performance. Highlights of the recommended
inspection procedures appear below. However, the full procedures as explained in the published
standard must be used.
DO NOT use a pipe grab that is structurally damaged. Such damage might include bent
jaws, deformation of the clevis or support pin(s), or damaged pipe guide weldments. Restore the grab to
normal operating condition BEFORE using it again.
- 13 -
Bekijk gratis de handleiding van Vestil PG-S-045, stel vragen en lees de antwoorden op veelvoorkomende problemen, of gebruik onze assistent om sneller informatie in de handleiding te vinden of uitleg te krijgen over specifieke functies.
Productinformatie
Merk | Vestil |
Model | PG-S-045 |
Categorie | Niet gecategoriseerd |
Taal | Nederlands |
Grootte | 6783 MB |