TABLE OF CONTENTS Rev. 2/22/2024 JIB-FM, MANUAL
TABLE OF CONTENTS Copyright 2021 Vestil Manufacturing Co. Page 6 of 12
ASSEMBLING THE CRANE
Numbers in parentheses correspond to part numbers in the EXPLODED VIEWS on pages 3, 4, and 5.
Step 1: Create a foundation with embedded reinforcing rods. The necessary minimum foundation
requirements for each JIB-FM model crane are provided in the diagrams and table below. When the
foundation is adequately cured, install
7
/
8
” jam nuts onto the anchor bolts (eight (8) total). Wind them to
the surface of the foundation. Level across the jam nuts by raising/lowering them as necessary to make
all of the nuts level. Create a mortar pedestal with grout, e.g. Morta Mix, inside the perimeter formed by
the jam nuts. See OVERHEAD VIEW OF FOUNDATION diagram below. The top of the grout pedestal
should be level with the tops of the jam nuts.
Step 2: Set the mast on the foundation. Align the bolt holes in the mounting plate with the anchor bolts
and carefully lower the mast onto the leveling nuts. Install
7
/
8
lock nuts on the anchor bolts but leave
them loose. Plumb the mast in 90° increments: Check the vertical levelness of the mast at 4 locations
equally spaced around the circumference of the mast. Adjust the leveling nuts as necessary to fine tune
mast levelness; then tighten the lock nuts against the mounting plate.
Mortar pedestal
(1” high)
Mast
Concrete
foundation with
reinforcing rods
A
o
u
n
d
at
io
n
4”
C
o
u
n
d
at
io
n
B
o
u
n
d
at
io
n
5
/
8
” reinforcing rod
3
/
4
” reinforcing rod
Reinforcing rods ~12”
centers on both sides
Model
A
B
C
D
JIB-FM-3
18”
15”
42”
14
1
/
2
JIB-FM-6
24”
19”
46”
14
1
/
2
JIB-FM-10
30”
23”
50”
17”
JIB-FM-20
30”
23”
60”
17”
JIB-FM-40
48”
41”
72”
24”
7
/
8
anchor bolts with
J hook (only one shown
in diagram; 8 required).
Threaded ends of
anchor bolts must
project ~5” above the
surface of the
foundation. Bolts must
be embedded to depth
“B” in foundation.
C
o
u
n
d
at
io
n
C
o
u
n
d
at
io
n
Overhead View of Foundation
Anchor
bolt hole
Mounting
plate
Mounting plate at
bottom of mast
Mortar pedestal in
center of bolt pattern
5”
ou
nd
ati
on
D
D
Inner bearing (28-110-001-001) Slides
onto a peg welded to the top of
the mast.
JIB-FM-40: The inner bearing must be
pinned to the top of the mast. At
this point, only set the inner bearing
in place but do not install the clevis
and cotter pins until after the socket
is set on top of the mast in Step 3.
Inner bearing
28-110-001-001
Clevis pin
28-112-049
Cotter pin
65077

Bekijk gratis de handleiding van Vestil JIB-FM-6, stel vragen en lees de antwoorden op veelvoorkomende problemen, of gebruik onze assistent om sneller informatie in de handleiding te vinden of uitleg te krijgen over specifieke functies.

Productinformatie

MerkVestil
ModelJIB-FM-6
CategorieNiet gecategoriseerd
TaalNederlands
Grootte2710 MB