3.6.1 Foundation Installation
If the foundation installation is used, the foundation must be built according to the requirements for
bottom installation holes and wiring holes of the energy storage system.
The energy storage system is heavy (<2.6t). Before building the foundation, the installation site
conditions (mainly geological conditions and environmental climate conditions, etc.) should be
investigated in detail. And then the design and construction of the foundation can be performed.
Foundation Requirements
Unreasonable foundation construction will bring great difficulties or troubles to the placement,
opening and closing of the energy storage system and later operation, therefore, the foundation of the
energy storage system must be designed and constructed in accordance with certain standards in
advance to meet the requirements of mechanical support, cable routing, and later maintenance.
The foundation should be constructed according to the following requirements at least:
* The foundation must ensure the stability and safety of the installation of the energy storage
system.
The foundation must have sufficient bearing capacity to effectively support the energy storage
system.
The soil at the installation site needs to be compact. If the soil is loose, take measures to
ensure that the foundation is stable.
The bottom foundation pit must be tamped and filled up.
The upper surface of the foundation must be at the same level (no more than 5 mm).
* The foundation should be higher than the natural floor to avoid erosion of the bottom and interior
of the energy storage system after rain or snowmelt water.
* Construct corresponding drainage measures according to local geological conditions.
* Build a cement foundation with sufficient cross-sectional area and height. The height of the
foundation is to be determined by the construction party according to the geology on site.
The excavated soil during the foundation construction should be cleared in time to avoid affecting the
subsequent forklift operation of the energy storage system..
When designing the direction of the air outlet, the wind direction of the installation site should be
considered.

Bekijk gratis de handleiding van V-Tac VT-12341, stel vragen en lees de antwoorden op veelvoorkomende problemen, of gebruik onze assistent om sneller informatie in de handleiding te vinden of uitleg te krijgen over specifieke functies.

Productinformatie

MerkV-Tac
ModelVT-12341
CategorieNiet gecategoriseerd
TaalNederlands
Grootte27251 MB