5.2.1 Safety Precautions
WARNING
Observe the safety operating rules of the crane at all times.
The hoisting work must be carried out in accordance with the hoisting requirements of
the MV Station.
Standing within 5 to 10 meters away from the hoisting areas is strictly prohibited!
Anybody standing under the boom or MV Station is strictly prohibited in the whole
hoisting process.
The hoisting work must be stopped on violent weather days. For example, in strong
wind, heavy rain, or thick fog conditions.
Precautions Before Hoisting
Use only specialized cranes, otherwise, it may result in personal injury or MV Station
damage.
All safety requirements must be met.
A professional instructor is required in the whole hoisting process.
Ensure the product is held steady and does not tilt during the whole hoisting process.
The tilt during hoisting should be ≤30°.
All the used slings must have the load-bearing capacity of at least 30t.
The crane should have sufficient arm length and radius of gyration.
Make sure the connections of slings are all secure and reliable, and the length of the
sling connected to each corner fitting is the same.
The length of the slings can be adjusted appropriately according to on-site conditions.
Hoisting the MV Station by connecting the four top corner fittings.
Some accessories may be required to ensure the safety during hoisting.
All doors of the MV Station are closed and locked.
Precautions During Hoisting
Ensure the product is held steady and does not tilt during the whole hoisting process.
The tilt during hoisting should be ≤30°.
Hoist the MV Station in a vertical manner. Do not drag or drop the MV Station on any
surface.
Keep the container stable and horizontal during hoisting, and ensure that the diagonal
gradient of the container is within 5 degrees.
The hoisting acceleration should not exceed 1.5g ("g” for gravitational acceleration).
When the MV Station has been hoisted for about 300mm away from the ground, stop to
check if all the connections are still firm. After confirmation, continue hoisting the MV
Station.
Lift and land the container slowly to prevent shock to the internal devices.
When transported to the final location, the MV Station should be put down slowly and
steadily.
System Manual5 Mechanical Installation
22

Bekijk gratis de handleiding van Sungrow MVS9000-LV, stel vragen en lees de antwoorden op veelvoorkomende problemen, of gebruik onze assistent om sneller informatie in de handleiding te vinden of uitleg te krijgen over specifieke functies.

Productinformatie

MerkSungrow
ModelMVS9000-LV
CategorieNiet gecategoriseerd
TaalNederlands
Grootte8876 MB