3.5 Ground Cable Installation
1. It is recommended to use copper wire for the chassis ground. Either solid conductor or
stranded wire is acceptable. Refer to local code standard for wire sizing.
2. Attach OT terminal: M5.
To connect the grounding terminal on the heat sink, please follow the steps below:
A
B
IMPORTANT
3. Strip the ground cable insulation to a suitable length.
4. Crimp a ring connector onto the cable and then connect it to the chassis ground terminal.
Figure 3.8 External Grounding Conductor Terminal
For multiple inverters in parallel , all inverters should be connected to the
same ground point to eliminate the possibility of a voltage potential existing
between inverter grounds.
User Manual
3. Installation
An external ground connection is provided at the both sides of inverter.
Prepare OT terminals: M5. Use proper tooling to crimp the lug to the terminal.
Connect the OT terminal with ground cable to the right side of inverter. The torque is 3.3N.m.
14
Figure 3.7 Connect the external grounding conductor
M5 Screw removed
Torque: 3.3N.m
Earth wire
Earth wire

Bekijk gratis de handleiding van Solis S6-EH3P12K02-NV-YD-L, stel vragen en lees de antwoorden op veelvoorkomende problemen, of gebruik onze assistent om sneller informatie in de handleiding te vinden of uitleg te krijgen over specifieke functies.

Productinformatie

MerkSolis
ModelS6-EH3P12K02-NV-YD-L
CategorieNiet gecategoriseerd
TaalNederlands
Grootte7082 MB