2.5 - CONDENSATION DRAIN
Thecondensationdrainnetworkmustbeopportunelydimensioned(minimuminternaldiameterofthepipe
mustbe16mm)andthepipelinemustbepositionedsoastoalwaysmaintainaspecicinclinealongtheroute,
neverlowerthan1%.Thedrainpipedirectlyconnectstooneofthetwodrainagebasins,positioneddown
onthesideshoulder,underthewaterconnectionsinfunctionofthetypeofinstallation:highwallorconsole.
- Ifpossible,makecondensationliquidowoutdirectlyinagutterorina“whitewater”drain.
- Incaseofdrainageintheseweragesystem,itisadvisedtocreateasiphontopreventtheperceptionof
badsmellstowardstherooms.Thecurveofthesiphonmustbelowerthanthecondensationcollection
basin.
- Ifcondensationmustbedrainedinsideacontainer,thelattermustremainopentotheatmosphereand
thepipemustnotbeimmersedinwater,avoidingproblemsofadhesivenessandcounterpressureswhih
wouldhinderfreeoutow.
- Ifadi󰀨erenceinlevelwhichwouldhindercondensationoutowmustbeovercome,itisnecessaryto
installapump(accessorykit).
Inanycase,pleaseconsultthespecicinstructionsinthecondensationdisposalpumpkit.
It is still opportune, at the end of installation, to check for correct outow of condensation liquid
by pouring water in the collection basin very slowly (approximately 1/2 l of water over approxi-
mately 5-10 minutes).
2.5.a-Highinstallationcondensationdrainagedeviceassembly(g.9)
a. Connectapipe(16)forliquidoutowtothedrainagejunctionofthecondensationcollectionbasin(15).
b. Lockitadequately.
c. Checkthatthedripedgeextension(17)ispresentandinstalledcorrectly.
2.5.b-Lowinstallationcondensationdrainagedeviceassembly(g.10)
a. Connectapipe(19)forliquidoutowtothedrainagejunctionofthecondensationcollectionbasin(18).
b. Lockitadequately.
c. Checkthatthedripedgeextension(20)ispresentandinstalledcorrectly.
Make sure the machine is perfectly levelled once installed, or with a slight in-
clination towards the direction of the condensation drain;
Insulate the delivery and return pipes well up to the entrance of the machine,
so as to prevent condensation dripping out of the collection basin itself;
Insulate the condensation drain pipe of the basin for its whole length.
2.6 - HOLDER ADJUSTMENT (Fig.11)
Theholderssuppliedtogetherwiththehydraulickitsallowforanadjustmentabletobalancetheloadlossesof
thesystem.Forcorrectadjustmentandbalancingofthecircuititisnecessarytofollowthefollowingprocedure::
a. Useascrewdrivertounscrewandextractthegrubscrewwithslotlocatedinsidethehexagonalsocket.
b. Closetheadjustmentscrewusinga5mmAllenwrench(4a).
c. Screwthegrubscrewwithslotuntilendoftravel.Thenmarkthereferencepointforadjustment(4b)with
a “x”.
d. Align the screwdriver to the “x”.
e. Openwithanumberofrotationsaccordingtothediagram∆p-Q(4c).

Bekijk gratis de handleiding van Olimpia Splendid Bi2 Wall TR, stel vragen en lees de antwoorden op veelvoorkomende problemen, of gebruik onze assistent om sneller informatie in de handleiding te vinden of uitleg te krijgen over specifieke functies.

Productinformatie

MerkOlimpia Splendid
ModelBi2 Wall TR
CategorieNiet gecategoriseerd
TaalNederlands
Grootte30074 MB