SERVICE & INTERIM BOILER WORK RECORD
It is recommended that your boiler and heating system are regularly serviced and maintained, in line with manufacturers’ instructions, and that the appropriate service /
interim work record is completed.
Service provider
When completing a service record (as below), please ensure you have carried out the service as described in the manufacturers’ instructions. Always use the
SERVICE/INTERIM WORK ON BOILER delete as appropriate
Date:
Engineer name: Company name:
Telephone N
o
: Gas Safe registration N
o
:
Max rate CO ppm CO
²
% CO/CO
²
Min rate CO ppm CO
²
% CO/CO
²
undertaken in accordance with manufacturers’
instructions, and readings are correct?”
yes
Gas rate: m
3
/h OR ft
3
/h
delete as appropriate Yes No
System inhibitor concentration has been checked and
appropriate action taken, in accordance with BS 7593
and boiler manufacturers’ instructions. *
yes n/a
Comments:
Signature:
instructions and BS 7593. It is only acceptable to not have undertaken this if the service engineers
attendance visit was in between annual services to attend a non-water facing component.
instructions and BS 7593. It is only acceptable to not have undertaken this if the service engineers
attendance visit was in between annual services to attend a non-water facing component.
instructions and BS 7593. It is only acceptable to not have undertaken this if the service engineers
attendance visit was in between annual services to attend a non-water facing component.
instructions and BS 7593. It is only acceptable to not have undertaken this if the service engineers
attendance visit was in between annual services to attend a non-water facing component.
instructions and BS 7593. It is only acceptable to not have undertaken this if the service engineers
attendance visit was in between annual services to attend a non-water facing component.
instructions and BS 7593. It is only acceptable to not have undertaken this if the service engineers
attendance visit was in between annual services to attend a non-water facing component.
SERVICE/INTERIM WORK ON BOILER delete as appropriate
Date:
Engineer name: Company name:
Telephone N
o
: Gas Safe registration N
o
:
Max rate CO ppm CO
²
% CO/CO
²
Min rate CO ppm CO
²
% CO/CO
²
undertaken in accordance with manufacturers’
instructions, and readings are correct?”
yes
Gas rate: m
3
/h OR ft
3
/h
delete as appropriate Yes No
System inhibitor concentration has been checked and
appropriate action taken, in accordance with BS 7593
and boiler manufacturers’ instructions. *
yes n/a
Comments:
Signature:
SERVICE/INTERIM WORK ON BOILER delete as appropriate
Date:
Engineer name: Company name:
Telephone N
o
: Gas Safe registration N
o
:
Max rate CO ppm CO
²
% CO/CO
²
Min rate CO ppm CO
²
% CO/CO
²
undertaken in accordance with manufacturers’
instructions, and readings are correct?”
yes
Gas rate: m
3
/h OR ft
3
/h
delete as appropriate Yes No
System inhibitor concentration has been checked and
appropriate action taken, in accordance with BS 7593
and boiler manufacturers’ instructions. *
yes n/a
Comments:
Signature:
SERVICE/INTERIM WORK ON BOILER delete as appropriate
Date:
Engineer name: Company name:
Telephone N
o
: Gas Safe registration N
o
:
Max rate CO ppm CO
²
% CO/CO
²
Min rate CO ppm CO
²
% CO/CO
²
undertaken in accordance with manufacturers’
instructions, and readings are correct?”
yes
Gas rate: m
3
/h OR ft
3
/h
delete as appropriate Yes No
System inhibitor concentration has been checked and
appropriate action taken, in accordance with BS 7593
and boiler manufacturers’ instructions. *
yes n/a
Comments:
Signature:
SERVICE/INTERIM WORK ON BOILER delete as appropriate
Date:
Engineer name: Company name:
Telephone N
o
: Gas Safe registration N
o
:
Max rate CO ppm CO
²
% CO/CO
²
Min rate CO ppm CO
²
% CO/CO
²
undertaken in accordance with manufacturers’
instructions, and readings are correct?”
yes
Gas rate: m
3
/h OR ft
3
/h
delete as appropriate Yes No
System inhibitor concentration has been checked and
appropriate action taken, in accordance with BS 7593
and boiler manufacturers’ instructions. *
yes n/a
Comments:
Signature:
SERVICE/INTERIM WORK ON BOILER delete as appropriate
Date:
Engineer name: Company name:
Telephone N
o
: Gas Safe registration N
o
:
Max rate CO ppm CO
²
% CO/CO
²
Min rate CO ppm CO
²
% CO/CO
²
undertaken in accordance with manufacturers’
instructions, and readings are correct?”
yes
Gas rate: m
3
/h OR ft
3
/h
delete as appropriate Yes No
System inhibitor concentration has been checked and
appropriate action taken, in accordance with BS 7593
and boiler manufacturers’ instructions. *
yes n/a
Comments:
Signature:

Bekijk gratis de handleiding van Intergas Xclusive 24, stel vragen en lees de antwoorden op veelvoorkomende problemen, of gebruik onze assistent om sneller informatie in de handleiding te vinden of uitleg te krijgen over specifieke functies.

Productinformatie

MerkIntergas
ModelXclusive 24
CategorieNiet gecategoriseerd
TaalNederlands
Grootte12726 MB