5. INSTALLER IMPORTANT POINTS
Please read all instructions before fitting this appliance
The installer shall instruct the user on the operation of the boiler, safety
devices contained within the boiler and on the location of the filling loop and
how to re-pressurize the system if the water pressure falls.
The installer should hand over the installation and user instructions upon
completion with the completed Benchmark Commissioning Checklist.
The service engineer must complete the service record on the Benchmark
Checklist after each service.
It is required under Gas Safe Regulations for the installation to be notified
to and registered with Gas Safe, Intergas and Building Control (Gas Safe
Notification).
During servicing the boiler the condensate trap and trap under the heat
exchange needs to be cleaned.
Before proceeding to commission the boiler check the gas inlet pressure is
20mbar (NG) or 37mbar for LPG.
Combustion analysis with a correctly calibrated and certificated analyzer is
essential for safe commissioning of the boiler.
A pressure reducing valve set to 3.5 bar must be fitted if supply mains
pressure is above 4 bar.
In hard water areas where the PH is 200ppm or above, appropriate
protection actions must be taken in accordance with BS 7593 in line with
building regulations Part L. (See T&C)
The user should be instructed to keep the instructions in a safe place for
servicing and future reference.
It is important to keep the boiler clear of dust during the installation. In
particular, do not allow debris to enter the flue connection at the top.
Before fitting the boiler ensure that the pipe work that you are installing is
connected to the appropriate connections on the boiler.
It is important to thoroughly flush the water circuits, after isolating the boiler, in
order to remove any fluxes, debris and all cleansing chemicals from the
system. This should be done particularly where boilers are being fitted to
existing radiator circuits (please refer to current Standard Codes of Practice).
Intergas recommend water treatment in accordance with the Benchmark
Guidance on Water Treatment in Central Heating Systems, we recommend the
use of FERNOX, SENTINEL or ADEY inhibitors. It is most important that correct
concentration of water treatment is maintained for the life of the boiler, a water
sample is required on installation and to be verified by the aforementioned
manufacturers should we attend a warranty call a water sample may be required
to keep the warranty valid. (BS 7593:2006)
This boiler has been factory set but adjustment may be required to the heating
input in order to match the individual heating demand. This can be done by
changing parameter 3 (= max. power CH) or parameter 4
(= max. power domestic water).
Please do not use the pressure relief valve as a means of flushing the system.
Remember that after hot water draw of a possible delay may occur before the
heating system will fire up.
All fluxes, residues and cleaner must be flushed from pipe-work and radiators
prior to commissioning.
External expansion vessels are best connected water side downwards to allow
correct draining/cleaning of system and to prolong the life of the vessel
diaphragm.
Note: an anti-cycle delay time can be set up to a maximum of 15 minutes by
adjusting parameter P as described in § 10.3.
If you experience any problems please refer to the installation and
commissioning guidelines within the boiler instruction manual. If necessary,
please contact Intergas Heating Ltd (See § 1.8)

Bekijk gratis de handleiding van Intergas Rapid 32 Plus, stel vragen en lees de antwoorden op veelvoorkomende problemen, of gebruik onze assistent om sneller informatie in de handleiding te vinden of uitleg te krijgen over specifieke functies.

Productinformatie

MerkIntergas
ModelRapid 32 Plus
CategorieNiet gecategoriseerd
TaalNederlands
Grootte10092 MB