7.2.2.2 System Operating Strategies of WIT 29.9-50K-XHU
TOU (Time of use):
Configure the system to work in the preset mode during different time segments
based on the peak-valley periods and electricity price. Setting items include: the
operating mode, enable/disable AC Charging function (charge from grid). During
the time not specifically configured, it will operate according to the system
settings.
Priority of power supplied to the loads:
2. Batteries;
3. Grid.
Self-consumption:
The WIT inverter prioritizes supplying the solar power and battery energy to the
loads. If Export Limitation is disabled, the surplus solar power can be fed to the
grid, but the battery energy will not be exported to the grid; if Export Limitation is
enabled, neither solar power nor battery energy would be sent to the grid. In case
that the solar power is insufficient, the battery will discharge to power the loads.
1. Solar panels;
NOTE: In Load First mode, a meter is required.
Set the forward power flow threshold A: once the load power on the external
meter is greater than this value, the inverter will reduce charging power and boost
power out until it reaches the maximum operating power of the WIT inverter.
Set the reverse power flow threshold B: once the grid feed-in power on the
external meter is greater than this value, the inverter will reduce output power
and boost charging power until it reaches the maximum operating power of the
WIT inverter.
Grid Peak Shaving:
5655

Bekijk gratis de handleiding van Growatt WIT29.9-50K-XHU, stel vragen en lees de antwoorden op veelvoorkomende problemen, of gebruik onze assistent om sneller informatie in de handleiding te vinden of uitleg te krijgen over specifieke functies.

Productinformatie

MerkGrowatt
ModelWIT29.9-50K-XHU
CategorieNiet gecategoriseerd
TaalNederlands
Grootte16744 MB