07 Equipment Commissioning
30
User Manual V1.2-2025-01-16
7 Equipment Commissioning
7.1 Checks before Power On
7.2 Power On
Step 1 Turn on the AC breaker between the inverter and the utility grid.
Step 2 Turn on the DC breaker of the inverter.
Transformer
Power
distribution
cabinet
PV
Grid
Inverter
AC Breaker
No. Check Item
1
The inverter is rmly installed in a clean place where is well-ventilated and easy to
operate.
2
The PE cable, DC input cable, AC output cable, and communication cable are connected
correctly and securely.
3 Cable ties are routed properly and evenly, and no burrs.
4 Unused ports and terminals are sealed.
5 The voltage and frequency at the connection point meet the on-grid requirements.
OFF
ON
2
1
Bekijk gratis de handleiding van Goodwe GW50K-SMT-L-G10, stel vragen en lees de antwoorden op veelvoorkomende problemen, of gebruik onze assistent om sneller informatie in de handleiding te vinden of uitleg te krijgen over specifieke functies.
Productinformatie
| Merk | Goodwe |
| Model | GW50K-SMT-L-G10 |
| Categorie | Niet gecategoriseerd |
| Taal | Nederlands |
| Grootte | 6698 MB |