07 Equipment Commissioning
30
User Manual V1.2-2025-01-16
7 Equipment Commissioning
7.1 Checks before Power On
7.2 Power On
Step 1 Turn on the AC breaker between the inverter and the utility grid.
Step 2 Turn on the DC breaker of the inverter.
Transformer
Power
distribution
cabinet
PV
Grid
Inverter
AC Breaker
No. Check Item
1
The inverter is rmly installed in a clean place where is well-ventilated and easy to
operate.
2
The PE cable, DC input cable, AC output cable, and communication cable are connected
correctly and securely.
3 Cable ties are routed properly and evenly, and no burrs.
4 Unused ports and terminals are sealed.
5 The voltage and frequency at the connection point meet the on-grid requirements.
OFF
ON
2
1

Bekijk gratis de handleiding van Goodwe GW50K-SMT-L-G10, stel vragen en lees de antwoorden op veelvoorkomende problemen, of gebruik onze assistent om sneller informatie in de handleiding te vinden of uitleg te krijgen over specifieke functies.

Productinformatie

MerkGoodwe
ModelGW50K-SMT-L-G10
CategorieNiet gecategoriseerd
TaalNederlands
Grootte6698 MB