07 Equipment Commissioning
53
Only for Australia: GW5000-SDT-AU30GW6000-SDT-AU30、GW8000-SDT-AU30
GW9990-SDT-AU30GW15K-SDTAU30、GW20K-SDT-AU30、GW25K-SDT-AU30
GW29K9-SDT-AU30、GW50K-SDT-C30.
Installing the Protecting Cover
7 Equipment Commissioning
7.1 Check Items Before Power ON
No. Checking Item
1
The inverter is 󽗉rmly installed in a clean place where is well-ventilated
and easy to operate.
2
The PE cable, DC input cable, AC output cable, and communication
cable are connected correctly and securely.
3 Cable ties are routed properly and evenly, and no burrs.
4 Unused ports and terminals are sealed.
5
The voltage and frequency at the connection point meet the on-grid
requirements.
7.2 Power On
Step 1 Turn on the AC switch between the inverter and the utility grid.
Step 2 (Optional) Turn on the DC switch between the inverter and the PV
modules.
Step 3 Turn on the DC switch of the inverter.

Bekijk gratis de handleiding van Goodwe GW50K-SDT-C30, stel vragen en lees de antwoorden op veelvoorkomende problemen, of gebruik onze assistent om sneller informatie in de handleiding te vinden of uitleg te krijgen over specifieke functies.

Productinformatie

MerkGoodwe
ModelGW50K-SDT-C30
CategorieNiet gecategoriseerd
TaalNederlands
Grootte11037 MB