07 Equipment Commissioning
32
User Manual V2.2-2025-07-24
7 Equipment Commissioning
7.1 Check Before Power ON
No. Check Item
1
The product is rmly installed at a clean place that is well-ventilated and easy to
operate.
2
The PE, DC input, AC output, and communication cables are connected correctly and
securely.
3 Cable ties are intact, routed properly and evenly.
4 Unused ports and terminals are sealed.
5
The voltage and frequency at the connection point meet the inverter grid connection
requirements.
7.2 Power On
Step 1 Turn on the AC switch between the inverter and the utility grid.
Step 2 Turn on the DC switch of the inverter.
AC Switch
Utility
Grid
PV String
Inverter
2
I
II (AU)
OFF
ON
OFF
ON
1
OFF
ON
OFF
ON
Bekijk gratis de handleiding van Goodwe GW10K-MS, stel vragen en lees de antwoorden op veelvoorkomende problemen, of gebruik onze assistent om sneller informatie in de handleiding te vinden of uitleg te krijgen over specifieke functies.
Productinformatie
| Merk | Goodwe |
| Model | GW10K-MS |
| Categorie | Niet gecategoriseerd |
| Taal | Nederlands |
| Grootte | 6944 MB |