Figure 75. Installation checklist online form QR code
9.1 Switching on the Green Motion Building EV charger
Before switching on the unit, please perform the checks below:
Step 1. Check that the equipment is correctly fixed to the wall or to the floor in accordance with local regulations.
Step 2. Check that the AC grid connections have been made correctly in accordance with local regulations.
Step 3. Perform checks on the continuity of the connections of the protective conductor, insulation resistance, RCD triggering
current, triggering time, etc., in accordance with local regulations.
Step 4. Verify that the connection cover is closed and secured with the fixing screws.
Step 1. Turn on the AC grid circuit breakers.
Step 2. Wait for the LED light to come on.
If the checks listed above were satisfactory, proceed as follows:
Before switching on the EV charger, check the effectiveness of the safety measure(s) of the system in accordance
with the local regulations.
Electrical systems or devices must be checked by professional and qualified personnel before commissioning and
switching on the unit.
9 Operation
Professional and qualified personnel must be experts in the field and are therefore responsible for commissioning
the system in accordance with the manufacturer’s instructions and local legislations.
Please visit the link or scan the QR code to fill out the installation checklist form at:
https://content.eaton.com/en-gb-installation-checklist-ev-chargers
97GREEN MOTION BUILDING INSTALLATION MANUAL MN191028EN April 2024 www.eaton.com

Bekijk gratis de handleiding van Eaton Green Motion XCI000411, stel vragen en lees de antwoorden op veelvoorkomende problemen, of gebruik onze assistent om sneller informatie in de handleiding te vinden of uitleg te krijgen over specifieke functies.

Productinformatie

MerkEaton
ModelGreen Motion XCI000411
CategorieNiet gecategoriseerd
TaalNederlands
Grootte16416 MB