11 | Commissioning
Installer reference guide
68
RZASG100~140MUV/Y
Sky Air Advance-series
4P743506-1 – 2023.08
NOTICE
If you cannot operate the unit in test run, see "11.5Error codes when performing a
test run"[470].
INFORMATION
During the first running period of the unit, the required power may be higher than
stated on the nameplate of the unit. This phenomenon is caused by the compressor,
that needs a continuous run time of 50hours before reaching smooth operation and
stable power consumption.
11.3 Checklist before commissioning
1 After the installation of the unit, check the items listed below.
2 Close the unit.
3 Power up the unit.
You read the complete installation instructions, as described in the installer reference
guide.
The indoor units are properly mounted.
In case a wireless user interface is used: The indoor unit decoration panel with infrared
receiver is installed.
The outdoor unit is properly mounted.
The following field wiring has been carried out according to this document and the
applicable legislation:
▪ Between the local supply panel and the outdoor unit
▪ Between the outdoor unit and the indoor unit (master)
▪ Between the indoor units
There are NO missing phases or reversed phases.
The system is properly earthed and the earth terminals are tightened.
The fuses or locally installed protection devices are installed according to this document,
and have NOT been bypassed.
The power supply voltage matches the voltage on the identification label of the unit.
There are NO loose connections or damaged electrical components in the switchbox.
The insulation resistance of the compressor is OK.
There are NO damaged components or squeezed pipes on the inside of the indoor and
outdoor units.
There are NO refrigerant leaks.
The correct pipe size is installed and the pipes are properly insulated.
The stop valves (gas and liquid) on the outdoor unit are fully open.
11.4 To perform a test run
This task is only applicable when using the BRC1E52 user interface.
Bekijk gratis de handleiding van Daikin RZASG140MUV, stel vragen en lees de antwoorden op veelvoorkomende problemen, of gebruik onze assistent om sneller informatie in de handleiding te vinden of uitleg te krijgen over specifieke functies.
Productinformatie
Merk | Daikin |
Model | RZASG140MUV |
Categorie | Airco |
Taal | Nederlands |
Grootte | 12296 MB |