11 Commissioning
In this chapter
11.1 Overview: Commissioning ...................................................................................................................................................... 61
11.2 Precautions when commissioning.......................................................................................................................................... 61
11.3 Checklist before commissioning............................................................................................................................................. 62
11.4 To perform a test run ............................................................................................................................................................. 62
11.5 Error codes when performing a test run................................................................................................................................ 64
11.1 Overview: Commissioning
This chapter describes what you have to do and know to commission the system
after it is installed.
Typical workflow
Commissioning typically consists of the following stages:
1 Checking the "Checklist before commissioning".
2 Performing a test run for the system.
11.2 Precautions when commissioning
WARNING
If the panels on the indoor units are not installed yet, make sure to power OFF the
system after finishing the test run. To do so, turn OFF operation via the user
interface. Do NOT stop operation by turning OFF the circuit breakers.
NOTICE
Before starting up the system, the unit MUST be energised for at least 6hours. The
crankcase heater needs to heat up the compressor oil to avoid oil shortage and
compressor breakdown during startup.
NOTICE
ALWAYS operate the unit with thermistors and/or pressure sensors/switches. If NOT,
burning of the compressor might be the result.
NOTICE
ALWAYS complete the refrigerant piping of the unit before operating. If NOT, the
compressor will break.
NOTICE
Cooling operation mode. Perform the test run in cooling operation mode so that
stop valves failing to open can be detected. Even if the user interface was set to
heating operation mode, the unit will run in cooling operation mode during 2‑3
minutes (although the user interface will display the heating icon), and then
automatically switch to heating operation mode.
Bekijk gratis de handleiding van Daikin AZAS140MUV, stel vragen en lees de antwoorden op veelvoorkomende problemen, of gebruik onze assistent om sneller informatie in de handleiding te vinden of uitleg te krijgen over specifieke functies.
Productinformatie
Merk | Daikin |
Model | AZAS140MUV |
Categorie | Niet gecategoriseerd |
Taal | Nederlands |
Grootte | 11332 MB |